发布网友 发布时间:2022-04-22 12:31
共1个回答
热心网友 时间:2023-10-13 20:14
AC:实际成本,actual cost
ACWP:已完工作实际成本,Actual Cost for Work Performed
BAC:完工预算,budget at completion
CCB:变更控制委员会,change control board
COQ:质量成本,cost of quality
CPAF:成本加奖励费用合同,cost plus award fee contracts
CPFF:成本加固定费用合同,cost plus fixed fee contract
CPI:成本绩效指数,cost performance index
CPIF:成本加激励费用合同,cost plus incentive fee contract
CPM:关键路径法,critical path activity
CV:成本偏差,cost variance
EAC:完工估算,estimate at completion
EF:最早完成日期,early finish date
EMV:预期货币价值,expected monetary value
ES:最早开始日期,early start date
ETC:完工尚需估算,estimate to complete
EV:挣值,earned value
EVM:挣值管理,earned value management
FF:完成到完成,Finish-to-Finish
FFP:固定总价合同,Firm-Fixed-Price Contract
FMEA:失效模式与影响分析,Failure Mode and Effect Analysis
FP-EPA:总价加经济价格调整合同,Fixed Price with Economic Price Adjustment Contracts
FPIF:总价加激励费用合同,Fixed Price Incentive Fee Contract
FS:完成到开始,Finish-to-Start
IFB:投标邀请书,Invitation for Bid
LF:最晚完成日期,Late Finish Date
LOE:支持型活动,Level of Effort
LS:最晚开始日期,Late Start Date
OBS:组织分解结构,Organizational Breakdown Structure
PDM:紧前关系绘图法,Precedence Diagramming Method
PMBOK:项目管理知识体系,Project Management Body of Knowledge
PV:计划价值,Planned Value
QFD:质量功能展开,Quality Function Deployment
RACI:执行、负责、咨询和知情矩阵,Responsible、Accountable、Consult、Inform Matirx
RAM:责任分配矩阵,Responsibility Assignment Matrix
RBS:风险分解结构,Risk Breakdown Structure
RFI:信息邀请书,Request for Information
RFP:建议邀请书,Request for Proposal
RFQ:报价邀请书,Request for Quotation
SF:开始到完成,Start-to-Finish
SOW:工作说明书,Statement of Work
SPI:进度绩效指数,Schele Performance Index
SS:开始到开始,Start-to-Start
SV:进度偏差,Schele Variance
SWOT:优势、劣势、机会与威胁,Strengths,Weaknesses,Opportunities,Threats
T&M:工料,Time and Material
WBS:工作分解结构,Work Breakdown Structure